NRMA Holiday Park

South West Rocks NSW

Alliance Construction Group (ACG) were awarded the contract to design & Construct of the upgrade to the NRMA South West Rocks Holiday Park. The works included survey, design and construction of the Stormwater Drainage, construction of new roads and final landscaping touches. The works were completed while the park was in operation which required a collaborative approach with our client, park management and patrons. Regular progress meeings were vital to maintain a well-managed, team effort and this ensured the success of the project.

Scope of Works included;

  • Provide Survey Services to pickup existing infrastructure
  • Design new stormwater drainage, kerb, and road pavements
  • Construction of Stormwater Drainage Pits and Pipes
  • Construction of Road Pavements and Kerb
  • Supply and Lay Asphalt Wearing Course
  • Regrade Camping/Caravan lots to new kerb levels.
  • Rehabilitate area to ensure quick turnaround for patrons to use the facility.

 

PROJECTS

ACG were awarded the contract to undertake much needed urgent road rehabilitation works due to landslides. The works were completed in steep conditions while the ground surface materials were still at times wet or holding moisture.
This design and construct work required careful thought prior construction; taking into consideration the existing ground conditions and natural fall of the ground and water in rain fall events to capture and divert water without the need for major excavations that would be costly to the client.
Works will be conducted to MidCoast Council specifications with all hold and witness points being adhered to. ACG liaise with the consultant and the Councils Engineer or Authorised Representative to ensure the project is complete to standard and with co-operation of all parties involved.