This project required the dismantling of a temporary steel bridge that had been installed on a side track. This involved disassembling the bridge components and carefully loading them onto transport vehicles. Once dismantled, the bridge was transported to its designated final location, where precise positioning was essential for its installation.
To accomplish this, a 90-ton mobile crane was utilized to lift and place the bridge components into position. The operation required careful coordination and planning to ensure the safe and accurate placement of each section.
Furthermore, the project team took proactive measures to minimize disruptions to public roads. This included detailed planning of traffic management strategies and coordination with relevant authorities to ensure smooth traffic flow during transportation and crane operations.
By meticulously planning the use of two separate cranes, implementing effective traffic control measures, and arranging transportation logistics, the project was executed with precision and efficiency while minimizing inconvenience to the public.